Carriageway Resurfacing of Liverpool Road
Published: 19/06/2018
Flintshire County Council, is pleased to announce funding has been secured to
carry out carriageway resurfacing at Liverpool Road, Buckley from the junction
of Smithy Lane to Rhuddlan Road.
The start date is Monday 25 June 2018 and it will take approximately three
weeks to complete the works.
To facilitate the resurfacing, a two-way traffic control will be in place for
the duration of the works with a 10mph speed limit within the works zone.
Access to individual properties and businesses will be maintained although
delays may be encountered.
Flintshire County Council and our contractor Roadway Civil Engineering Ltd
apologise for any delay and disruption that may be caused as a consequence of
this essential maintenance work and will undertake the works as quickly as
possible.